Supplier Quality Evidence and FAT Preparation

A factory video is not a complete quality plan, and a FAT promise is not useful without a test basis. This page is for buyers defining pre-contract evidence and factory acceptance requirements. Prepare the project specification, container, target output, inspection points, documents and responsibilities. The next step is to agree what will be demonstrated, what will be recorded and who closes each unresolved item before shipment.

Prepare My Evidence List

Buyer working asset

Evidence request table

Evidence group Request before contract Confirmation point
Project response Specification, scope, exclusions and interface list Technical agreement
Engineering Layout, utilities, key drawings and document schedule Drawing approval
Manufacturing Relevant equipment evidence and agreed inspection access Inspection plan
FAT Protocol, materials, output basis, checks and records Protocol approval
Handover BOM, manuals, spares, packing list and open-item status Shipment release

Buyer working asset

FAT basis questions

  • Which machine or connected package is tested?
  • Which bottle, cap, label and pack materials are used?
  • What output basis and test duration apply?
  • Which utilities are simulated or excluded?
  • Which quality and safety points are recorded?
  • Who witnesses in person or remotely?
  • How are deviations, evidence and retest handled?
  • Who approves shipment release?

Buyer working asset

Open-item closure register

Finding Evidence required Owner Due point
Performance gap Retest record or approved technical disposition Named supplier engineer Before shipment release
Document gap Approved revision or written delivery date Document owner Before packing or agreed milestone
Cosmetic or assembly item Dated photo/video and inspection record Manufacturing owner Before loading
Site-dependent item Written site-condition dependency and responsible follow-up Buyer and supplier Before contract shipment approval

Buyer working asset

Connect the evidence plan to supplier decisions

Check who provides the evidence

Verify the company, payment and manufacturing records behind the response.

Continue

Compare written FAT scope

Normalize protocols, trial materials, records and closure responsibilities.

Continue

Coordinate multi-factory findings

Assign every shared finding to a named supplier or buyer owner.

Continue

Include evidence in the brief

Send the required records and acceptance basis with the project request.

Continue

Last reviewed:

Next purchasing action

Write the evidence and FAT basis before contract.

This page supports supplier review and does not replace independent inspection or technical due diligence.